Line stopped, CIP not running, changeover kit at the station, gasket in hand. If any of the four is missing, stop here.
#
Do this
Figure
3
Lock out the filler drive at the MCC breaker and keep the key on you
breaker F2-14
4
Open the bowl drain valve and let it run until the flow stops
5
Confirm the bowl pressure gauge reads zero before touching the guard
0 bar
10
Hand-start all four bolts before tightening any
11
Tighten in a diagonal cross pattern, in two passes
12 Nm
The line that makes a card falsifiable
Derived from OPS-06 Rev 4. The day OPS-06 reaches Rev 5, the operator standing here can see that this page predates it, without checking a register, without asking anyone, and without the card having to be wrong.
Stop and call the shift lead if
The gauge reads above zero after the drain. The seat face is scored. The interlock light stays red with the bolts tight.
Page 1 of 1198 words100%
How to write work instructions and job aids
A work instruction is a step-by-step guide to one task at a specific machine or workstation, cut down from the standard operating procedure (SOP) that governs it. A good one fits on one page and names the station, its own revision and the procedure revision it came from. Each action is a short command, figures such as torques get their own column, and the page says when to stop and who to call. A job aid is a shorter prompt for trained people, such as a laminated card.
The copy hanging at the station is the one people follow, so write for someone with one hand free and make every copy show its revision.
Charts clipped above each bench keep the reference where the work happens. Photo: Remy Gieling on Unsplash
Purpose, scope, roles and the whole process, with reasons
Work instruction
A trained person at one station
Steps, figures and stop conditions on one page
Quick reference card
Someone who knows the task well
About seven lines of sequence and who to call
Job breakdown sheet
A trainer teaching someone new
Important steps, key points and reasons
Cut the procedure down to one station
Work from the written procedure, never from memory. If several versions circulate, first settle which one is in force: an SOP library gives each procedure one current document. If none exists, record someone doing the job and turn the walkthrough into an SOP.
Then count the stations. The same task on different equipment needs separate pages: a changeover at a hand-fill bench and one at an automatic filler are different sequences. Split by machine, position and who does it, never by shift. Cut each page in this order until it fits on one side.
1
Cut the reasons
Explanations of why stay in the procedure.
2
Cut scope and definitions
Who it covers and what terms mean stay there too.
3
Cut other people's steps
Drop anything done away from this station.
4
Cut branches that never happen here
Keep only the situations this station meets.
What's left is the sequence, the numbers and the conditions that stop the work. If that still won't fit, you have two instructions.
Keep the knack with its step. The Lean Enterprise Institute describes Training Within Industry, a set of World War II training programs that Toyota later adopted. Its Job Instruction trainers split each job into important steps, key points and reasons why3. On the page, a step and its key point (the detail that makes it work or keeps you safe) share a line.
Fixing weak steps
Problem
Weak
Better
Passive voice
"The drain valve should then be opened."
"Open the drain valve."
Two actions in one
"Remove the guard and lift out the bowl."
Split it: "Remove the guard." "Lift out the bowl."
Figure kept elsewhere
"Torque to spec (see manual)."
"Torque the bolts in a cross pattern," with 12 Nm in the figure column.
No finish line
"Seat the gasket."
"Seat the gasket until the witness line is covered."
Copy each figure from the procedure or manual, never from memory. HSE says not to refer readers to a table in a manual kept elsewhere for torque settings1, and asks that quantities match what the controls and displays show.
Lay out the work instruction page
Put a control block at the top of every copy. The EU guide says instruction documents should be uniquely identifiable2, with a defined effective date. Six fields cover it: instruction ID, station, revision, parent procedure and its revision, issue date and verification date.
End with no more than three stop conditions, each naming something the person can see and who to call. "If the gauge reads above 0 bar after draining, stop and call the shift lead" is a stop condition. "Beware of residual pressure" is only a warning.
ExamplePart of a work instructionAn illustrative example written for this guide.
WI-031 Mixer blade change. Station: Line 3 mixer. Rev 1.2. Derived from OPS-14 Rev 5. Issued March 3, 2026. Verified March 10, 2026.
4. Lock out the mixer at breaker B3-07 and keep the key on you.
5. With everyone clear, try to start the mixer at the panel: nothing should move.
6. Return the panel controls to Off.
9. Tighten the blade nut in two passes. Figure: 40 Nm.
Stop and call the maintenance lead if the mixer moves at step 5.
Traceable. Naming the procedure revision means a newer OPS-14 flags this page for review.
Tests the isolation. Step 5 proves the lockout worked instead of assuming it.
Lockout, confined spaces and regulated manufacturing have their own rules, and those come first. Ask whoever handles safety or quality compliance to review the instruction. This guide is general practice, not compliance advice.
Then verify it. Someone who doesn't use the instruction watches an operator follow it, checks each figure against the machine plate and asks what the page gets wrong. OSHA requires this independence for lockout procedures: the inspection, due at least once a year, must be done by an authorized employee other than the ones using the procedure4.
When the parent procedure changes, review every instruction cut from it. Many will be unaffected or need only rewording. Where the work itself changes, pull old copies before new ones go up, and retrain people before they start. OSHA's lockout standard requires retraining whenever there is a change in the energy control procedures4.
Each figure has its own column and matches its source
The control block names the parent procedure's revision
Three stop conditions at most, each naming who to call
Someone who doesn't use it has watched it used
Old copies are pulled and every new one is logged
For a faster start, open this template with Edit with AI. River cuts your procedure into one page per station and logs every copy you tell it about.
How to use this template
Use the files as they are, or open them in River. On your own, start with the Work Instruction Format and the filled One-page Job Aid, cut one page for each station, then log every instruction and every copy in the sheets.
With Edit with AI, River reads the procedure you send, counts the stations it covers and cuts a page for each. Send photos of the cards already posted, too. River records the revision printed on each one, never adds a figure your procedure doesn't state, and leaves every page unverified until someone checks it at the station.
1
Download it or open it in River
Get the four Word documents and four CSV sheets free, or open the template in River and send your procedure.
2
Cut one page per station
Count the stations your procedure covers, then cut one page for each with the Work Instruction Format, or let River draft them.
3
Log every copy
Give each laminated card, binder page and photocopy a row in the Point of Use Log, with the revision printed on it.
4
Verify it at the station
Have someone who doesn't use the page watch it in use, record the result, and revise what fails before you reprint.
What's in the template
One procedure, three stations, ten copies hanging upThe register keys on the station. The log keys on the physical copy. Neither one is a list of documents.
Work Instruction and Job Aid Template
Instruction Register
Calibri11
Instruction Register
Illustrative rows for a fictional contract canner, Hollow Creek Beverage, 90 staff, two lines.
ID
Task
Station
Cut from
Parent now
Rev
State
WI-014
Filler bowl changeover
Line 2 inline filler
OPS-06 Rev 4
Rev 4
2.1
Current
WI-015
Filler bowl changeover
Line 1 hand-fill bench
OPS-06 Rev 3
Rev 4
1.0
Orphaned
WI-008
Conveyor jam clearance
Line 2 accumulation table
SAF-01 Rev 5
Rev 6
3.0
Orphaned
WI-019
Date coder reel change
Line 1 and Line 2 coders
OPS-11 Rev 1
Rev 1
1.1
Two stations, one card
WI-030
CIP hose connection
CIP skid
none
n/a
1.0
No parent
WI-026
Brix check
Blend tank 2
QC-07 Rev 4
Rev 4
0.3
Draft
WI-004
Rinser nozzle strip
Line 1 rinser
OPS-02 Rev 3
Rev 3
2.0
Withdrawn
WI-014 and WI-015 are the same task from the same procedure. One revision of OPS-06 moved both of them and only one was re-derived. A register keyed on the task holds that as a single row and the hand-fill bench disappears.
WI-030 is a finding, not an error. A taped sheet describing a task the procedure library has never heard of means the work is real and nothing governs it, which is the fastest possible start on a procedure somebody was always going to need.
Cut from and Parent now are separate columns on purpose. When they disagree, the instruction is orphaned.
Point of Use Log
Calibri11
Point of Use Log
One row per physical copy. The revision is transcribed from the copy, never looked up.
Copy
Where it hangs
Medium
On copy
In force
State
C-101
Line 2 filler guard rail
Laminated 4x6
2.1
2.1
Current
C-102
Supervisor binder, tab 6
Binder page
1.8
2.1
Stale, pull
C-104
Maintenance crib
Photocopy
2.2
3.0
Unaccounted
C-105
Line 1 palletiser tablet
Live document
live
live
No pull needed
C-108
Line 2 coder cabinet
Laminated 4x6
1.0
1.1
Stale, pull
C-109
CIP skid door
Taped A4 sheet
none
n/a
No revision printed
C-110
Line 1 rinser frame
Laminated 4x6
2.0
withdrawn
Pulled 20 Mar
C-104 is the copy that makes this sheet worth keeping. Nobody issued it, nobody knows how long it has been in the crib, and it is one revision behind an instruction whose isolation point has since moved to the MCC breaker.
C-109 is not stale and it is not current. A copy with no revision printed on it cannot be shown to be either, so reading it and deciding is not a control. It gets reissued with a control block instead.
C-105 is the argument for a tablet at the stations that change most: a live document has no copy to pull, ever.
Verification Record
Calibri11
Verification Record
Somebody who does not use the instruction, watching it being used at the machine.
Machine
Instr.
Date
Performed by
Independent
Outcome
Line 2 inline filler
WI-014
2 Apr 26
J. Okoro
Yes
Failed, revised
Line 2 accumulation table
WI-008
18 Feb 26
J. Okoro
Yes
Passed
Line 2 seamer
WI-021
8 Jan 26
H. Bracken
Yes
Passed with action
Line 1 palletiser
WI-011
5 Mar 25
J. Okoro
Yes
Overdue
Line 1 hand-fill bench
WI-015
30 Jun 25
K. Sowa
No
Invalid
Line 1 and 2 coders
WI-019
never
none
n/a
Never verified
WI-014 failed and that is the point. The card said 18 Nm and the machine plate said 12. Reading the figure column against the plate takes a minute, it is the highest-yield check available, and no amount of document control finds it.
WI-015 was verified by the operator who uses it, which establishes nothing. The row is recorded as invalid with no next-due date, because setting one twelve months out on a station nobody watched is how a bench goes three years unexamined.
The four facts here are the machine, the date, the people included and the person performing. Named individually, not as a checkbox.
Work Instruction FormatThe layout for one page: a six-field control block, a figure column, stop conditions and what to leave out.
What a Parent Revision ObligesWhat to do when a procedure changes: which instructions to review, which copies to pull and who to retrain.
One-page Job AidA filled 15-step instruction for a filler bowl changeover, with notes on why it's laid out that way.
Quick Reference CardA seven-line card for a 4 by 6 inch laminate, and three conditions a task must meet to earn one.
Instruction Register sheetOne row per instruction and station, with the procedure revision it was cut from and the one in force.
Point of Use Log sheetOne row per physical copy: where it hangs, what it's printed on and the revision it shows.
Version Control sheetEach revision: what changed, why, whether retraining is needed, copies to pull and who approved it.
Verification Record sheetEach check at the station: machine, date, people included, who verified and whether they were independent.
Common questions
What should a work instruction template include?
A control block, numbered steps and stop conditions. The control block carries the instruction's ID, station and revision, the parent procedure and that procedure's revision, and the issue and verification dates. Each step is one command with its figure in a separate column, and up to three stop conditions say what to watch for and who to call.
What is the difference between an SOP and a work instruction?
An SOP governs a whole process, while a work instruction covers one task at one station. The SOP holds the purpose, scope and responsibilities, for managers, auditors and trainers. The instruction holds only what the person doing the task needs: steps, figures and stop conditions. It changes more often, so it carries its own revision and the SOP revision it came from.
What is a job aid?
A job aid is a short prompt used during the task, such as a checklist, a diagram or a laminated quick reference card. It helps a trained person get the sequence right without relying on memory. It does not replace training: someone new to the task needs the full instruction and a person to show them.
How long should a work instruction be?
One side of one page. A longer one usually covers two stations or still carries the procedure's explanations, so split it or cut the reasons. A quick reference card is shorter still: about seven lines of sequence, with 10 as the ceiling, small enough to laminate at 4 by 6 inches.
How often should work instructions be reviewed?
Whenever the parent procedure, the equipment or the materials change, and whenever a check at the station finds a problem. Add a fixed check too, such as once a year. For lockout procedures in the US, OSHA requires an inspection at least annually by an authorized employee other than those using it.
Is this work instruction template free?
Yes. Download the four Word documents and four CSV sheets with no signup. The sheets and the sample job aid use a fictional canning plant, so you can see every column in use before you clear it. Edit with AI opens the same template in River.
What does Edit with AI do?
It opens the template in a free River workspace. River asks for your procedure and photos of the cards at your stations. Then it counts the stations, cuts one page for each and logs the copies you describe or photograph. It never invents a figure your procedure doesn't state, and it ends by asking which station to verify first.
Chandler has spent the last six years working in AI, building tools for millions of users and Fortune 100 companies. In 2025, he co-founded River to build a new kind of operating system for AI agents.